Solano Community College

Measure Q Project Updates

The Measure Q Bond was passed in November 2012.  The Citizens of Solano County invested in their futures by voting to improve and expand the facilities of the Solano Community College District with the passage of the Measure Q Bond.  The projects listed below are the currently active projects and their status.

November 2021

Fairfield Campus Active Project Updates

Library/LRC

(Click to View Project Summary)

Project Site Camera

Library/Learning Resource Center – Fairfield Campus

Description: Replacement of existing Building 100 Library with new 59,252sf Library/LRC, demo of old Library and old portable buildings.

Budget:  $45,948,000 ($24,300,000 Measure Q; $20,148,000 State; $1,500,000 Redevelopment pass-through funds)

Status: First level T-Bar ceilings, exterior sunshades, and temporary fiber optic bridge are complete.  Second level book shelving is also complete.  First and second levels interior storefront installation is nearing completion. The elevators, exterior doors and hardware are also nearing completion.

Completion Target: April 2022

 Early College High School Portables

 (Click to View Project Summary)

Early College High School Portables - Fairfield Campus

Description: Installation of two (2) new portables classrooms and associated sitework for the Early College High School Program.  

Budget:  $790,000

Status: DSA Certification received. Project complete.

Completion Target: November 2021

Vehicle and Pedestrian Signs 

 (Click to View Project Summary)

 

Pedestrian & Vehicle Wayfinding Signs - Fairfield Campus

Description: Design/installation of new exterior vehicle wayfinding signs and the procurement of pedestrian signs to provide necessary wayfinding information.  

Budget:  $170,767

Status: Six (6) Pedestrian Signs have been installed on campus.

Completion Target: December 2021

 B1800B Roof Canopy

(Click to View Project Summary)

B1800B Exterior Roof Canopy - Fairfield Campus

Description: Replacement of a failing existing roof structure serving an outdoor lab space for students learning to use welding equipment and various pieces of machinery.  

Budget:  $650,000

Status: Received DSA certification letter.  Project is closed out with DSA.

Completion Target: November 2021

  Baseball & Softball Clubhouse Replacement

 (Click to View Project Summary)

Baseball and Softball Clubhouse Replacement - Fairfield Campus

Description: Replacement of the existing clubhouses used by the Baseball and Softball programs with DSA approved modular buildings.  

Budget:  $860,000

Status: Bid Phase complete for general contractor. Submittal review underway for modular buildings.

Completion Target: August 2022

Solar Energy

(Click to View Project Summary)

 

 

5 Megawatt Solar Installation (Solar Energy) - Fairfield Campus

Description: Work done under this project is to add solar production to the District's Fairfield Campus with the application of solar photovoltaic arrays.  The project goal is to completely offset current energy consumption with the potential of over production (up to 5 megawatts) for the Fairfield Campus.  The project includes the following components:  feasibility study, assessment, planning, design, construction, and operation/maintenance.

Budget:  $13,000,000

Status: Request for Qualifications/Proposals issued.

Completion Target: April 2023

On Campus Housing

(Click to View Project Summary)

 

On-Campus Housing - Fairfield Campus

Description: Work done under this project is to evaluate and assess the need for and feasibility of on-campus housing at the Fairfield Campus. The project begins with needs assessment and a feasibility analysis.  If housing is deemed viable, a likely P3 (Public-Private Partnership) Project will proceed.

Budget:  $500,000

Status: In Pre-Design Phase.

Completion Target: April 2022

Exterior Painting New Bldg Number

(Click to View Project Summary)

 

 

 

 

Fairfield Campus Building Exterior Painting (Phase 1 & 2)

Description:
Phase 1 - Exterior painting of Buildings 500, 600, 700, 800, and 900, and addition of building accent colors and numbers throughout the campus for enhanced way-finding.
Phase 2 - Complete exterior painting of buildings 300, 400, 1000, 1300, 1400, 1600, 1700, 1800, 1800B, 2600 and miscellaneous painting at other areas on campus.

Budget:  $1,000,000

Status:
Phase 1 - Closeout complete. Phase 1 complete.
Phase 2 - Project Closeout.

Completion Target:
Phase 1 - November 2021
Phase 2 - January 2022

ADA Improvements

(Click to View Project Summary)

 

 

 

 

ADA Improvements (ADA Transition Plan) - Fairfield Campus

Description: Update the existing ADA Transition Plan to ensure that buildings; infrastructure improvements; programs, services, and activities are accessible under current ADA requirements.

Budget:  $240,795

Status: ADA Surveying is complete and the report is being drafted. Work on the Self-Evaluation of Policies and Procedures is underway.

Completion Target: June 2022

B300 Renovation

(Click to View Project Summary)

 

 

 

 

Building 300 Renovation - Fairfield Campus

Description: Work done under this project will be to renovate existing Building 300 on the Fairfield Campus.  The project goal is to modernize the aging building in order to meet current standards. The project includes the following components:  feasibility study, assessment, planning, design and construction.

Budget:  $3,000,000

Status: Initial Study/Feasibility Report complete.

Completion Target: To-Be-Determined

Early Learning Center Expansion

(Click to View Project Summary)

 

 

Early Learning Center Expansion - Fairfield Campus

Description: Expansion of the Early Learning Center to serve approximately forty (40) children. This will require the addition of a new building to the Early Learning Center location. This project will also include upgrades to the exterior play areas as determined by regulations/code. This project is anticipated to require DSA review and approval.

Budget:  $2,500,000

Status: Design Development Phase underway. Coordination between Architect of Record and Modular Manufacturer ongoing.

Completion Target: January 2023

Vacaville Center Active Project Updates

 VV Annex Corbels

(Click to View Project Summary)

Vacaville Center Annex Building Corbels Removal - Vacaville Center

Description: Repair corbels.

Budget:  Part of Phase 2 renovations with a total budget of $3,812,147

Status: Punch List work ongoing.

Completion Target: December 2021 (Phase 2)

Aeronautics Sewer Connection and Parking Exp. 

 (Click to View Project Summary)

Aeronuatics - Sewer Connection and Parking Expansion Project - Vacaville

Description: Remove septic system and connect to City/County sewer line.  Add 16 spaces adjacent to existing parking lot.  

Budget:  $535,000

Status: City of Vacaville Building Department review ongoing.

Completion Target: To-Be-Determined